Data Centre Register Sign in free

Home › Data centres › Brazil

Data centres in Brazil

As of 16 October 2026, the Data Centre Register lists 129 data centres in Brazil with 510 MW of live IT capacity and 9,575 MW in the pipeline (368 MW under construction, 726 MW committed and 8,481 MW at an early stage).

129data centres
510 MWlive IT capacity
9,575 MWin the pipeline
368 MWunder construction

Capacity by stage

StageSitesIT capacity
Live96510 MW
Under construction20368 MW
Committed9726 MW
Early stage48,481 MW
Land banked0–
No capacity listed0–

A site counts in the most advanced stage that has capacity listed. Pipeline is under construction, committed and early stage together.

Largest operators in Brazil

OperatorSitesLive MWPipeline MW
Scala181194,962
Elea Data Centers13133,473
Ascenty28129156
CloudHQ20264
Tecto317206
OMNIA10200
ODATA56162
Ada Infrastructure20100

Cities

CitySitesLive MWPipeline MW
Eldorado do Sul104,750
Rio de Janeiro16323,201
Sao Bernardo do Campo20333
Santana de Parnaíba850223
Paulínia25232
Caucaia10200

Types of data centre

Brazil has 109 colocation and 20 self-build data centres. By category: Wholesale (59), Retail (46), Self-build Financial/Institutional (8), Self-build Public Cloud (6), Build-to-suit (4), Self-build Public Sector (2). Ready-for-service years listed run from 2000 to 2028.

See every Brazil site on the map

The register has a record for each of these 129 sites: operator, address, coordinates, capacity by stage, ready-for-service year and sources. Sign in with Google for a free account: 5 full site records and 100 sites in lists a day. Pro (US$49 a month) opens 300 records a day, full query lists and Ask AI.

Frequently asked questions

How many data centres are there in Brazil?
The Data Centre Register lists 129 data centres in Brazil as of 16 October 2026: 96 live, 20 under construction, 9 committed and 4 at an early stage, of which 109 colocation and 20 self-build.
What is the data centre capacity of Brazil?
Brazil has 510 MW of live data centre IT capacity, with a further 9,575 MW in the pipeline (368 MW under construction, 726 MW committed and 8,481 MW at an early stage), for 10,085 MW in total.
Which operators have the most data centre capacity in Brazil?
By total IT capacity listed, the largest operators in Brazil are Scala, Elea Data Centers and Ascenty. Scala has 18 sites with 5,081 MW.
Where are the data centres in Brazil?
The cities with the most data centre capacity in Brazil are Eldorado do Sul, Rio de Janeiro, Sao Bernardo do Campo and Santana de Parnaíba.
Where does this data come from?
The Data Centre Register at globaldcwiki.com is built from a register of data centre sites. Every proposed change is checked against outside sources and accepted by an admin before it appears. Figures were last updated on 16 October 2026.

Other data centre markets

Last updated 16 October 2026. Cite as: Data Centre Register, "Data centres in Brazil", https://www.globaldcwiki.com/data-centres/brazil.