As of 16 October 2026, the Data Centre Register lists 14 data centres operated by ODATA in 4 markets, with 180 MW of live IT capacity and 452 MW in the pipeline (88 MW under construction, 84 MW committed and 280 MW at an early stage).

14data centres
180 MWlive IT capacity
452 MWin the pipeline
88 MWunder construction

Markets

MarketSitesLive MWPipeline MW
Mexico468224
Colombia36144
Brazil56162
Chile24522

Capacity by stage

StageSitesIT capacity
Live12180 MW
Under construction288 MW
Committed084 MW
Early stage0280 MW
Land banked0–
No capacity listed0–

A site counts in the most advanced stage that has capacity listed. Pipeline is under construction, committed and early stage together.

Cities

CitySitesLive MWPipeline MW
Palo Alto130195
Osasco11236
Hortolândia12416
San Bernardo12713
Coyotillos11517
Cota2624

Types of data centre

ODATA has 14 colocation and 0 self-build data centres in the register. By category: Wholesale (10), Build-to-suit (3), Retail (1). Ready-for-service years listed run from 2010 to 2026.

See every ODATA site on the map

The register has a record for each of these 14 sites: operator, address, coordinates, capacity by stage, ready-for-service year and sources. Sign in with Google for a free account: 5 full site records and 100 sites in lists a day. Pro (US$49 a month) opens 300 records a day, full query lists and Ask AI.

Frequently asked questions

How many data centres does ODATA operate?
The Data Centre Register lists 14 data centres for ODATA as of 16 October 2026: 12 live, 2 under construction, 0 committed and 0 at an early stage.
What is ODATA's data centre capacity?
ODATA has 180 MW of live data centre IT capacity listed, plus 452 MW in the pipeline, for 632 MW in total.
Where does ODATA have data centres?
ODATA's largest markets by IT capacity are Mexico, Colombia, Brazil and Chile.
Where does this data come from?
The Data Centre Register at globaldcwiki.com is built from a register of data centre sites. Every proposed change is checked against outside sources and accepted by an admin before it appears. Figures were last updated on 16 October 2026.

Other data centre operators

Last updated 16 October 2026. Cite as: Data Centre Register, "ODATA data centres", https://www.globaldcwiki.com/operators/odata.