Cirion data centres

As of 16 October 2026, the Data Centre Register lists 16 data centres operated by Cirion in 8 markets, with 50 MW of live IT capacity and 82 MW in the pipeline (62 MW under construction, 20 MW committed and 0 MW at an early stage).

16data centres
50 MWlive IT capacity
82 MWin the pipeline
62 MWunder construction

Markets

MarketSitesLive MWPipeline MW
Brazil41760
Chile21210
Peru21110
Argentina242
Colombia350
Venezuela110
Panama110
Ecuador100

Capacity by stage

StageSitesIT capacity
Live1550 MW
Under construction162 MW
Committed020 MW
Early stage00 MW
Land banked0–
No capacity listed0–

A site counts in the most advanced stage that has capacity listed. Pipeline is under construction, committed and early stage together.

Cities

CitySitesLive MWPipeline MW
Rio de Janeiro2360
Lima Metropolitan Area21110
Cotia1130
Buenos Aires242
Bogotá250
Caracas110

Types of data centre

Cirion has 16 colocation and 0 self-build data centres in the register. By category: Retail (14), Wholesale (2). Ready-for-service years listed run from 2000 to 2026.

See every Cirion site on the map

The register has a record for each of these 16 sites: operator, address, coordinates, capacity by stage, ready-for-service year and sources. Sign in with Google for a free account: 5 full site records and 100 sites in lists a day. Pro (US$49 a month) opens 300 records a day, full query lists and Ask AI.

Frequently asked questions

How many data centres does Cirion operate?
The Data Centre Register lists 16 data centres for Cirion as of 16 October 2026: 15 live, 1 under construction, 0 committed and 0 at an early stage.
What is Cirion's data centre capacity?
Cirion has 50 MW of live data centre IT capacity listed, plus 82 MW in the pipeline, for 132 MW in total.
Where does Cirion have data centres?
Cirion's largest markets by IT capacity are Brazil, Chile, Peru, Argentina and Colombia.
Where does this data come from?
The Data Centre Register at globaldcwiki.com is built from a register of data centre sites. Every proposed change is checked against outside sources and accepted by an admin before it appears. Figures were last updated on 16 October 2026.