Data Centre Register Sign in free

Home › Operators › Applied Digital

Applied Digital data centres

As of 16 October 2026, the Data Centre Register lists 4 data centres operated by Applied Digital in 1 market, with 57 MW of live IT capacity and 850 MW in the pipeline (125 MW under construction, 225 MW committed and 500 MW at an early stage).

4data centres
57 MWlive IT capacity
850 MWin the pipeline
125 MWunder construction

Markets

MarketSitesLive MWPipeline MW
United States457850

Capacity by stage

StageSitesIT capacity
Live257 MW
Under construction0125 MW
Committed0225 MW
Early stage2500 MW
Land banked0–
No capacity listed0–

A site counts in the most advanced stage that has capacity listed. Pipeline is under construction, committed and early stage together.

Cities

CitySitesLive MWPipeline MW
Ellendale Township150350
Scandinavia Township10300
Fargo10200
Fried170

Types of data centre

Applied Digital has 3 colocation and 1 self-build data centres in the register. By category: Self-build Crypto (1), Build-to-suit (1), Wholesale (1). Ready-for-service years listed run from 2022 to 2028.

See every Applied Digital site on the map

The register has a record for each of these 4 sites: operator, address, coordinates, capacity by stage, ready-for-service year and sources. Sign in with Google for a free account: 5 full site records and 100 sites in lists a day. Pro (US$49 a month) opens 300 records a day, full query lists and Ask AI.

Frequently asked questions

How many data centres does Applied Digital operate?
The Data Centre Register lists 4 data centres for Applied Digital as of 16 October 2026: 2 live, 0 under construction, 0 committed and 2 at an early stage.
What is Applied Digital's data centre capacity?
Applied Digital has 57 MW of live data centre IT capacity listed, plus 850 MW in the pipeline, for 907 MW in total.
Where does Applied Digital have data centres?
Applied Digital's largest markets by IT capacity are United States.
Where does this data come from?
The Data Centre Register at globaldcwiki.com is built from a register of data centre sites. Every proposed change is checked against outside sources and accepted by an admin before it appears. Figures were last updated on 16 October 2026.

Other data centre operators

Last updated 16 October 2026. Cite as: Data Centre Register, "Applied Digital data centres", https://www.globaldcwiki.com/operators/applied-digital.